Introduction
Amidst a flurry of cases during the early years of adjudication, the courts appear to have achieved their aim of resolving questions thrown up by the 1996 Housing Grants Construction and Regeneration Actand creating a reliable process for the pursuit of adjudication-related claims (Fenn et al, 2008). Increasingly, however, jurisdictional challenges have reduced the effectiveness of Adjudication and increased the cost of the process (The Scottish Executive, 2004). In 2010, a study by theGlasgowCaledonianUniversityfound that upwards of 25% of challenges to the Adjudicators jurisdiction were related to whether the contract was in writing (Kennedy et al, 2010). Against the backdrop of recent court decisions, it is clear that case law concerning the requirement for written agreements is still at an evolutionary stage. Given these developments and impending changes to the legislation, it is timely to reflect upon case law concerning written agreements and assess the impeding changes to the HGCRA on challenges to this aspect of Adjudicators’ Jurisdiction.
The nature of the Adjudicators’ Decision
Order custom essay Adjudicators` Jurisdiction and Construction Contracts with free plagiarism report
We know that the construction industry is inherently litigious and most construction contracts are adversarial in nature. Even under partnering conditions, if the contract is complex, there is likely to be a possibility of dispute (Lowsley et al, 2006). Parties to contracts and other parties in dispute within the construction industry have the opportunity to seek a remedy in court or through various forms of alternative dispute resolution. The creation of the Scheme for Construction Contractsand the Housing Grants Construction and Regeneration Act led to the development of the alternative methods of dispute resolution first proposed by in the Latham Report (Latham, 1994). Adjudication was introduced on a statutory basis under the Housing Grants Construction and Regeneration Act 1996.
Adjudication in the construction industry is a process that provides for the referral of a dispute arising under the contract at any time, to a person (an adjudicator) who has to act impartially on the basis of such information as the parties to the dispute are able to provide him, or he is able to ascertain for himself within a very limited timescale. He reaches conclusions as to the parties’ rights and obligations under their contract on the basis of the information provided by the parties.The decision being set out in a decision that is contractually binding on the parties until the original decision is finally determined in legal proceedings or by arbitration (if the contract so provides for between the parties) or by agreement between the parties. Adjudication is therefore not final and not binding. The dispute is not settled by adjudication, although it may be if the parties choose to accept the adjudicator’s decision as final.
Once the adjudicator has made his decision on the rights of the parties under contract, it is for the parties to decide whether they agree with those conclusions, or have the dispute heard again by a tribunal that will give them a decision that us final and binding, i.e. by litigation or arbitration. The parties are quite at liberty not to accept the adjudicator’s decision, although they are bound by the decision, temporarily at least. Adjudication by itself does not and cannot resolve the dispute. For the dispute to be resolved each party has to decide for itself that it is going to take the matter no further.An adjudicator states what his conclusions are as to the rights and obligations of the parties.This decision may be based upon very limited information. It certainly will have to be made in a limited time.Both these factors may well mean that the adjudicator’s reaches leaves a lot to be desired.The adjudicator certainly may not have sufficient time to make a full forensic investigation. It may be that the adjudicator considers that the dispute is of such a nature that it is totally impossible for him to reach any sort of conclusion.
Adjudicators’ Jurisdiction
Upon receipt of the notice of adjudication, the party receiving may object to the proposed adjudication. Almost the only way that a party can stop an adjudication proceeding is by alleging that the adjudication lacks jurisdiction, i.e. the authority to deal with the issues raised.If an adjudicator proceeds without the necessary jurisdiction his decision will not be enforceable. On the other hand if he fails to proceed when he does have jurisdiction, then that is unjust to the referring party. Examples of grounds on which jurisdictional challenges may be made are as follows:
- The contract is not a construction contract within the 1996 Act;
- The relevant activities are not construction operations within the Act
- The contract is not in writing within the scope of the Act
The adjudicator was not properly appointed, for example, because he is not the adjudicator named in the contract, the wrong adjudicator nominating body made the appointment, the appointment was too late, or the adjudicator has a conflict of interest
It is asserted that there is no dispute
The points are collectively known as objections to the jurisdiction. In these circumstances, it is vital that, should they wish to do so, the party receiving not only restate their objections at the outset of the process but also maintain and preserve that objection throughout the adjudication. A failure to do so may result in that party being taken to have consisted to an ad hoc adjudication and thereby bound by a decision reached.
To refer a dispute to adjudication, a construction contract must exist (Royce, 2009). Examples abound where parties have argued that all or part of the contract is not ‘in writing’ to avoid any liability. The courts have considered this aspect on a number of occasions and held that no contract exists where the agreement is too ambiguous to constitute a contract.
What constitutes a contract in writing is an interesting question and fundamental to adjudication, but who decides if a contract is in writing Does the adjudicator have the power to decide If no contract exists, then it follows that the Adjudicator has no jurisdiction under the 1996 Act. However, Adjudicators do not have power to decide on their own jurisdiction. Many adjudicators face this challenge and either decide to resign or continue to act. Typically, the decision is based on objective criteria and takes into account factors such the price and scope of works, as well as start and completion dates (Green, 2006).
Oral and Written Agreements: The provisions of the HGCRA
The question of whether the Act applies is only an agreement in existence has come before the English Court of Appeal to decide. This decision is of particular importance because it is commonplace in the construction industry for substantial work to be undertaken on the strength and basis of an oral agreement. Whilst oral agreements may be binding on the parties, the difficulty arises in determining the precise terms of that agreement in the absence of clear written evidence.It is for this reason that section 107 of the Act should apply only to written contracts. Thus, unless the construction contract is an ‘agreement in writing’ there is no right to adjudicate under the Act. This means that oral contracts are not subject to adjudication under the Act. There is a complicated definition of what is meant by the term agreement ‘in writing’.Section 107(1)-(6) of the HGCRA 1996 states:
‘107 Provisions applicable only to agreements in writing
- The provisions of this Part apply only where the construction contract is in writing, and any other agreement between the parties as to any matter is effective for the purposes of this Part only if in writing. The expressions “agreement”, “agree” and “agreed” shall be construed accordingly.
- There is an agreement in writing— (a) if the agreement is made in writing (whether or not it is signed by the parties), (b) if the agreement is made by exchange of communications in writing, or c) if the agreement is evidenced in writing.
- Where parties agree otherwise than in writing by reference to terms which are in writing, they make an agreement in writing.
- An agreement is evidenced in writing if an agreement made otherwise than in writing is recorded by one of the parties, or by a third party, with the authority of the parties to the agreement.
- An exchange of written submissions in adjudication proceedings, or in arbitral or legal proceedings in which the existence of an agreement otherwise than in writing is alleged by one party against another party and not denied by the other party in his response constitutes as between those parties an agreement in writing to the effect alleged.
- References in this Part to anything being written or in writing include its being recorded by any mean’.
The ‘in writing’ requirement has been applied wholesale to the entire substantive agreement, as endorsed by the Court of Appeal decision in RJT Consulting Engineers v DM Engineering (Northern Ireland) Ltd [2002] All ER (D) 108 (Mar)).
In RJT Consulting Engineers, the Technology andConstruction Courtheld that the documentary evidence and written material between the two parties was sufficient to bring their agreement within the adjudication proceedings.Accordingly the declaration sought by RJT that the agreement was not an agreement in writing for the Act was refused.
The matter then came before the Court of Appeal, which overturned the decision of the TCC. RJT argued that there had been confusion regarding documents consistent with there being a contract and documents, which constituted a record of the entirety of the oral agreement. RJT maintained that the whole agreement had to be evidenced in writing in order to provide the certainty, which would enable the adjudicator to move swiftly to a decision within the short timetable provided by the Act. DM countered that all that was necessary was that there should be evidence in writing of the existence of a contract in writing, whether that would be the identities of the parties, and the price and nature of the works to be undertaken.
The Court of Appeal agreed with RJT. The Invoices and other extensive evidence relied on by DM was simply evidence of the existence of contract. It was not evidence of the terms of the oral agreement between the parties. Section 107 of the Act details what has to be evidenced in writing is literally the agreement, which means all of it, not just part of it. The only exception to that generally is where relevant parts of an oral agreement are alleged and not denied in written submissions in adjudication.The appeal was allowed however it was noted that what is more important is that the terms of the agreement material to the issues giving rise to the adjudication should be clearly recorded in writing. Written evidence of all the material terms would therefore suffice. The material terms of the agreement must be recorded in any one of the forms prescribed by section 107 of the Act for the requirements of that section to be met and for the agreement to constitute a ‘construction contract’.
For a claimant to seek to say that a contract is evidenced in writing pursuant to section 107 (4) of the Act, they must show that the writing evidenced the whole of the agreement and not just part of the agreement as was the case in Debeck Ductwork Installation Ltd v T&E Engineering Ltd.However, in Cowlin Construction Limited v CFW Architects (2002), only a little over a month later, HHJ Kirkham held that “
‘It appears that the contract was made partially in writing and partly oral. It is clearly evidenced in writing. Pursuant to section 107(2) of HGCRA, this was a construction contract’.
Whereas, in Carillion Construction Limited v Devonport Royal Dockyard (2002) HHJ Bowsher held that if a variation to the terms of a contract is agreed orally, this must be recorded or evidenced in writing, failing which an adjudicator will not have jurisdiction to decide disputes arising under the oral agreement. While some suggest that the debate surrounding the requirement to satisfy section 107 have largely been resolved (ref), some controversy remains. In RJT the Court of Appeal decided that the whole of the terms of the agreement (not just the fact of an agreement) must be evidenced in writing, but scope to depart from the ‘RJT’ principle does exist in particular circumstances. In Connex South Eastern Ltd v MJ Building Services Group Ltd (2004), for example, the court held that there was no oral aspect to the underlying contract (i.e. the meeting minutes confirmed that Connex accepted M J Building’s tender in its entirety) and therefore the Act did apply, whereas in the RJT Court of Appeal case it was found that part of the underlying contract was oral, and, as that part of the oral contract had not been evidenced in writing the Act did not apply.
In light of the foregoing, it seems that the process of deciding what is considered evidenced in writing and what is not is fraught with difficulty. The apparently restrictive interpretation of section 107 of the Act by the Court of Appeal in RJT remains of real concern within the industry, particularly among the smaller firms who may fall outside the provisions of the 1996 Act. Concern within the industry was expressed as early as 2004 in a report by the Construction Umbrella Bodies (The Construction Umbrella Bodies Adjudication Task Group, 2002). The report recommended that in respect of ‘evidenced in writing’, the law should be clarified particularly in light of the RJT case, to avoid undermining the adjudication process altogether if left unresolved. Certainly, the RJT decision has considerably limited the right to adjudicate where no written contract agreement exists, but the decision was reached not because the court wished to restrict the right to adjudicate, but as LJ Ward foresaw, the difficulty an adjudicator would have making a decision based on an alleged oral agreement within the tight timeframe provided by the process (Brawn, 2010).Indeed, as LJ Ward stated:
‘Certainty is all the more important when adjudication is envisaged to take place under a demanding timetable. The adjudicator has to start with some certainty as to what the terms of the contract are’
Nevertheless, there is still controversy about the effect of section 107 as construed in RJT.Some within the construction industry wish to abolish the requirement so that all construction contracts even those which are oral or partly in writing are covered by the Act (Bowes, 2007) (akin to legislation inNew South Wales); others prefer the status quo (Kennedy et al, 2010).
Contracts in writing: recent developments
A closer examination of the precise terminology of the 1996 Act is fundamental to our understanding of the law concerning contracts in writing and the nature of what constitutes the formation of a contract.The Act uses wording such as ‘by reference to terms that are in writing’. There is no reference to a ‘previous agreement that is in writing’. Indeed, there is no provision for adjudication in relation to an alleged construction contract made orally or otherwise not evidenced in writing –see Carillion Construction Limited. This would be contrary to the provisions of section 107 (1) of the Act. What constitutes a construction contract What is the basis of the agreement There must obviously be agreement on scope, price and time. On the contrary, what if there was no agreement over timeCertainly there would be an implied term within the contract that the works will be completed within a reasonable time, but does this provide us with certainty that a contact exists where the scope and price are more precise What if the contract alluded to reasonable costs incurredWhat if the identity of the parties was uncertain What if the scope of works was based on subsequent instruction or orders, which may or not be set down in writing In such circumstances is there any guidance we can draw upon as to what constitutes a construction contractSection 107 of the Act only applies where there is a contract in writing, meaning that all material terms must be in writing; see RJT as the leading authority in the area. Justice Jackson has also provided additional guidance on the constitution of a construction contract more recently in the case of Mast Electrical v Kendall (2007).Justice Jackson noted that a thorough analysis of correspondence, meeting minutes and so on was warranted to establish whether a contracted ever concluded between parties. He also noted that where there had been performance ‘the court would lean in favour of finding a contract if it could probably do so’. What if there was no agreement on all the material terms between the partiesUnder the RJT case principles there would be no contract, but the contractor would have entitlement to a quantum meruit under contract law provisions.In all circumstances, courts would be obliged to follow the principles established within RJT. In other words, as Brawn (2010, pg 37) noted, either:
- ‘The contract must be in writing;
- Established by means of communication in writing;
- Evidenced in writing;
- Agreed by reference to terms in writing; or
- Exchange of submissions in proceedings in which the existence of contract is alleged by one party and not denied by the other party’
The decision of the court in Hart Investments Limited v Fidler (2006) provides a further example of an authority in this area.
In terms of the role of the Adjudicator, they should adopt a rigorous approach when determining whether minor issues said to have been agreed orally between parties prevent an otherwise written contract pursuant to section 107 of the Act being considered as a contract in writing.
The exercise itself must be objective and take into account the nature of the contract and the parties themselves. Nevertheless, what may be a minor issue in one contract may not be minor in another one. In for example, a 10 million pound project an oral agreement on different types of architectural ironmongery may be a minor issue but a major one on another development.The adjudicator will also need to consider the intention of the parties, and whether they intend to give affect to their oral agreement such that it becomes binding in written form at later stage. On the other hand, a later oral agreement may not be binding on parties because it lacks consideration or because it was not intended to be binding, as in the case of Allen Wilson Joinery Ltd v Privetgrange Construction Ltd [2008].
There remains a great deal of legal uncertainty about the effect of subsequent oral amendments to written contracts or oral variations to the scope of works, to the extent that differences of opinion have emerged among legal practitioners.
While some consider that the right to adjudicate is lost under the 1996 Act, others consider the right to adjudicate unaffected, particularly with respect to oral amendments to the works. The debate has provided a fertile ground for challenges to the Adjudicator’s jurisdiction under the Act.Indeed, what if the written terms of the contract were incomplete or further terms agreed orally, or significant changes to the scope of works agreed on an oral basisIs there any guidance we can draw upon in such circumstances The answer to this question is yes.For instance, in Hatmet v Herbert (2005), there was sufficient written evidence as to the scope of the work, price and timeframe, but little information on the basis of price revision.In these circumstances the provisions of section 15 of the Sale of Goods Act (1992) such that an implied term would apply that would require a reasonable price be paid for any price revision.In Carillion Construction Ltd v Devonport Royal Dockyard Ltd (2005), a written contract was varied mid-way into the works by an oral agreement. This changed the basis of the payment to a cost-reimbursable one. The court held that the adjudicator had no jurisdiction to decide whether an oral agreement varied the written. The adjudication was deemed invalid by the court under the prescriptions of the Act.
Letters of intent are a common feature of the contract-forming process in the construction industry, but do they have any currency under the provisions of section 107 of the ActThe answer to this question is no. Where the works are undertaken under a letter of intent it will be difficult, but not impossible, to demonstrate an agreement in writing exists as prescribed under section 107.This is because by the time a dispute has arisen further agreements have usually been made that are either inferred from conduct, where they agreed orally, or not evidenced by the letter of intent.
It is also common for parties to rely on particular documents as evidence that a contract exists during adjudication, but are there any legal implications under the provisions of the 1996 Act. The answer to this question is yes. Where a party, relies upon a particular document as evidence of a contract when adjudicating, it will be bound by the terms within that document.
Subsequently, if evidence emerges that there are other terms not recorded in that document, even if they are recorded in other documents, then if the adjudicator takes those other documents into account in his decision, that decision is unlikely to be enforced by the courts. In for example, Redworth Construction v Brook dale Healthcare (2006) the court concluded that while the ‘contract’ referred to adjudication, it did not meet the RJT test of an agreement in writing as prescribed under section 107.
In terms of agreements as to the scope of works and subsequent oral variations, there are three noteworthy cases. In Deback v T&E Engineering (2002), the contract between the parties was not adequately evidenced in writing because the fax relied upon by the plaintiff did not sufficiently establish the scope of works. In Management Solutions Professional Consultants Limited v Bennett (Electrical) Services Limited [2006] and ALE Heavylift v MSD (Darlington) Limited [2006], the parties waived the need for instructions to vary the scope of works to be confirmed in writing.The argument upheld by the courts was the absence of confirmation in writing did not take the contract outside the scope of section 107 of the Act. The principle being that where a written contract provides that instructions allowing variations to the scope of works are permissible if confirmed in writing, a contract in writing still exists even if the instruction given under the authority of the contract is not confirmed in writing.
What about the inclusion of implied terms in a construction contract Does this transform an otherwise written contract into one that is no longer written under the provisions of section 107 of the Act The answer to this question is no. According to Royce (2009) ‘it was manifestly not the intention of parliament to exclude from the jurisdiction of an adjudicator an agreement solely because it contains implied terms’, as endorsed by the court in Connex South Eastern Ltd and more latterly Allen Wilson v Privetgrange Construction [2008]. Rather the parliament intentions were to avoid a situation whereby one or other party would suggest that a contract, otherwise not complete under the provisions of section 107, could be completed after execution by virtue of implied terms representing the ‘unexpressed intention’ of either party,, as noted in Galliford Try Construction Ltd v Michael Heal Associates Ltd [2003]. We know that implied terms operate by virtue of the law. Such terms are implied into contracts for different reasons. Whereas, some terms are implied into contracts to give effect [for example, business efficacy] to a contract, other terms are implied to provide context to the actual relationship between parties. Should we differentiate between different types of implied terms within the context of section 107 The answer to this question is no according to Royce (2009). Thus there is no reason why any type of implied terms d transforms an otherwise written contract into one not covered by the provisions of the 1996 Act see for example,Allen Wilson v Privetgrange Construction [2008], as an example of an authority in this area.
The remaining provisions of Section 107 merit closer scrutiny. This is because they provide other means by which agreements can be made in writing under the provisions of the 1996 Act.
- Section 107 (4) states
‘An agreement is evidenced in writing if an agreement made otherwise than in writing is recorded by one of the parties, or by a third party, with the authority of the parties to the agreement’.
- Section 107 (5) states:
‘An exchange of written submissions in adjudication proceedings, or in arbitral or legal proceedings in which the existence of an agreement otherwise than in writing is alleged by one party against another party and not denied by the other party in his response constitutes as between those parties an agreement in writing to the effect alleged’..
The wording of Section 107 (5) is controversial and worthy of closer examination. The wording seems to suggest that if one party to adjudication alleges the existence of an oral agreement under their terms and the other party does not deny the agreement on this basis, then there will be an agreement in writing.
Thus, in spite of the ruling in RJT it does seem possible to create a written agreement from an oral agreement which is oral or partly oral if the agreement is asserted in written submissions in an adjudication, arbitration or legal proceedings and the other party does not deny that agreement. It is difficult to believe that Parliamentary intentions were to create something so manifestly unjust. Is there any guidance we can draw upon. The answer to this question is yes.
In, for example, Grovedeck v Demolition [2000], the court held that section 107(5) had a narrow focus. In other words, it only applies where an oral agreement has been admitted in a previous adjudication, but most responding parties will raise an RJT jurisdictional challenge on the basis of section 107 in that first adjudication. Thus, a party who does not raise the challenge first time will lose the right to challenge on that ground in subsequent adjudications. However, is it also worth looking at the precise wording of section 107 (5) against the backdrop of parliamentary intentions and deliberations at this point.
An examination of the proceedings of the House of Lords for 23rd July 1996 on the wording of section 107(5) reveals no mention of ‘adjudication proceedings’. It seems the upper chamber of parliament incorporated an amendment proposed by the House of Commons, in which the words ‘in adjudication proceedings or’ would immediately follow the word ‘submission’. According to Royce (2009) parliament’s intention was to make reference to to ‘other, prior’ adjudication proceedings, not to provide an adjudicator with jurisdiction over proceedings for which he did not have at appointment based upon submissions made by one party to otherwise unauthorised adjudication proceedings.
We know that amendments to the Act will repeal Section 107 of the 1996 Act in its entirety. This will mean that adjudication provisions will apply to all construction contracts whether written or oral, or even partly in writing and partly oral. However, the new Act will also amend section 108(2) whereby all the provisions setting out the required adjudication procedures will have to be in writing. If they are not in writing the Scheme for Construction Contracts will apply.
There have been two recent cases that have caused some confusion among practitioners in relation to contracts in writing. In T & T Fabrications v Hubbard [2008], the decision of an adjudicator was not enforced on the basis that certain terms of the contract relating to the provision of drawings and the timing of the works were not in writing. The terms went to the scope, quality and essential of the works and there was a genuine dispute as to whether these terms had been agreed. Therefore there was an arguable case that the terms of the contract were not in writing. However in the second case, Allen Wilson Joinery v Privetgrange Construction Limited [2008] it was held, firstly, that implied terms do not prevent a contract from being in writing and, secondly, that a budget price with a final price to be agreed does not prevent there being a contract in writing.
The removal of section 107 of the Act, and so the requirement for a construction contract to be in written form , may render the RJT principles and subsequent legal judgements ineffectual, however, it is important to note that, until the amendments to the Act come into force, the case law remains effective.
The Construction Act 2009: implications of impeding change to the requirements for contracts in writing
The Local Democracy, Economic Development and Construction Act – the Construction Act 2009 -received Royal Assent in July 2009 (Brawn, 2010), however, no date has yet been set for it to come into force.The new legislation amends Part II of the Housing Grants, Construction and Regeneration Act 1996. The main benefits of the new Act, as conceived by the Government, was to improve cash flow in the construction supply chains and encourage parties to resolve disputes by adjudication rather than by arbitration or litigation (Gwilliam, 2010).
The main changes effected by the new Act are:
- Adjudicators will no longer be limited to contracts in writing;
- Adjudicators will be able to correct their decision if a clerical or typographical error is made; and
- Parties will not be able to agree a term which provides for who is to bear that costs of an adjudication until after the adjudicator has been appointed.
The most significant change is the abolition of the requirement for contracts in writing. The amendment will apply across the new Act and cover the payment provisions. This will mean that even purely oral agreements will now have to incorporate the payment provisions and the need for notices (Brawn, 2010). Nevertheless, some claim that the deletion of the requirement for contracts to be in writing will create greater uncertainty for the adjudication process, leading to a greater potential for injustice. Agreement on material terms, however trivial, is undeniable and for adjudication to be available these have to be in writing.This level of certainty provides the adjudicator with a greater sense of intentions and nature a contract.
However, there is a perception that the current mechanism is open to abuse, particularly by those with the greatest bargaining power (Gwilliam, 2010). The new legislation may not only provide smaller contractors, often less adept at dealing with contractual matters with greater protection against abusive practices, but also greater access to the adjudication process itself: many verbal contracts or written agreements involving oral variations typically involve smaller, more financially vulnerable sub-contracting firms.
It will be interesting to see how the amendments will operate in practice. We can only speculate on the likely impact on industry at this time. However, where oral or part – oral contracts are within the scope of the adjudication process, inNew South WalesandQueenslandfor instance, distinct case law is notable by its absence (Glover 2007). This suggests that the proposed amendments to HGCRA may not be as problematic as some commentators anticipate: it is more commercially- astute to have written agreements in any case. While the new provisions are unlikely to have an impact in cases where there are formal contracts which incorporate adjudication clauses, the changes are more likely to have an impact where there letters of intent are involved and where written contracts are based on standard terms and conditions supplemented by verbal agreements.
While the legislative changes may not have an impact on the role of the Adjudicator, it will affect their modus operandi. The adjudicator will need to find additional time to consider the formation of the verbal contract to ascertain the precise intentions of the parties. Inevitably, where oral agreements are concerned, adjudicators will also need to consult witnesses and where differing views exist there will be need to probe witness statements through some form of cross-examination process. This is likely to be highly contentious, potentially giving rise to grievances, injustice and challenges to adjudicators ‘decisions. Potentially, more hearings are likely to take place and it is also possible that adjudicators may need additional time to consider the more substantive, complex issues at the core of a dispute. Paradoxically, the new rules will make it even more important that agreements are in written form. Indeed, it may prompt parties to draft agreements incorporating every, possible clause, as well as those limiting the agreement to the contents of that contract. While this may not necessarily prevent any disagreements, it may improve the position of parties in the event that a dispute arises as to the material terms of a contract itself.
References
- Bowes, D (2007) Practitioners’ perception of adjudication inUKconstruction. In: Boyd, D (Ed) Proceedings of the 23rd Annual ARCOM Conference, 3-5 September 2007, Belfast, UK, Association of Researchers in Construction Management, 117-125.
- Brawn, D (2010) The circumstances in which an adjudicators decision is unenforceable or inappropriate in construction disputes, International journal of arbitration, mediation and dispute management, volume 76, Number 3, August.
- Dancaster, C (2008) Construction Adjudication in theUnited Kingdom: Past, Present, and Future, J. Profl. Issues in Engrg. Educ. and Pract. 134, 204.
- Fenn, P and O’Shea,M (2008) Adjudication: Tiered and Temporary Binding Dispute Resolution in Construction and Engineering, J. Profl. Issues in Engrg. Educ. and Pract. 134, 203.
- Glover, J (2007) adjudication in Australia: an overview, Proceedings of the Adjudication Society Annual Conference, 15 November, pg 4, http://www.fenwickelliott.co.uk/files/Adjudication%2022%20-%20Adjudiation%20in%20Australia%20-%20an%20overview.pdf
- Green, M (2006) Construction Adjudication and the Definition of Disputes: an Analysis of Recent Case Law, Proceedings of the 2006 COBRA conference, Bartlett School, UCL, London, 7-8th September
- Gwilliam, R (2010) Open season on AmbushHow disputes have changed, Society of Construction Law, Paper D110, June.
- Housing Grants Construction and Regeneration Act 1996, HMSO,London
- Latham, M (1994) Constructing the team: final report – Joint Review of Procurement and Contractual Arrangements in theUnited Kingdom, Construction Industry. HMSO
- Lowsley, S and Linnet, C (2006) About Time: Delay Analysis in Construction, Royal Institute of Chartered Surveyors,Coventry
- Ndekugri, I and Russell,V (2006) Disputing the existence of a dispute as a strategy for avoiding construction adjudication, Engineering, Construction and Architectural Management, Vol. 13 Iss: 4, pp.380 – 395
- Kennedy, P (2008) Evolution of Statutory Adjudication as a Form of Dispute Resolution in theU.K.Construction Industry, J. Profl. Issues in Engrg. Educ. and Pract. 134, 214
- Kennedy, P and Milligan, J (2008) Mission Drift in Statutory Adjudication, Proceedings of the COBRA 2007 Conference, Georgia Institute of Technology, Georgia, USA, 6-7 September.
- Kennedy,P, Milligan, J, Cattanach, L and McCluskey, L (2010) The development of Statutory Adjudication in the UK and its relationship with construction workload, RICS COBRA 2010 conference, Dauphine-Paris University, 2nd-3rd September, ISBN 9781842196199.
- Khatib, J and Blagden, A (2006) Has Adjudication been accepted as an Effective Form of Dispute Resolution within the UK Construction IndustryConstruction Industry Quarterly Volume: 8, Issue: 4, 181-184.
- Royce, D (2009) Adjudication: Recent Development, http://construction.practicallaw.com/6-204-4037 (access on 28th July 2011)
- The Construction Umbrella Bodies Adjudication Task Group (2002) Guidance for Adjudication, July, www.cic.org.uk/adjudication/adjudicationinfo.htm
- The Local Democracy, Economic Development and Construction Act 2009, HMSO,London
- The Scheme for Construction Contracts Regulations 1998 (EnglandandWales) Regulations (1998), SI 1998/649, HMSO,London
- The Scottish Executive (2004) Improving Adjudication in the Construction Industry: A report on Consultation & proposals, May, Scottish Executive
Cases
- Bennett (Electrical) Services Ltd. v. Inviron Ltd. [2007] EWHC 49 (TCC)
- Hart Investments Limited v. Fidler [2006] EWHC 2857 (TCC)
- Allen Wilson Joinery Ltd v Privetgrange Construction Ltd [2008] EWHC 2802 (TCC)
- Group Connex South Eastern Ltd v MJ Building Services PLC [2004] BLR 333
- Galliford Try Construction Ltd v Michael Heal Associates Ltd [2003] EWHC 2886 (TCC)
- Grovedeck Ltd. v. Capital Demolition Ltd. [2000] B.L.R. 181, 185
- RJT Consulting case (RJT Consulting Engineers v DM Engineering (Northern Ireland) Ltd [2002] All ER (D) 108 (Mar)
- Redworth Construction v Brookdale Healthcare (2006) 110 ConLR 77)
- Carillion Construction Ltd v Devonport Royal Dockyard Ltd [2005] EWCA Civ 1358)
- Management Solutions Professional Consultants Limited v Bennett (Electrical) Services Limited [2006] EWHC 1720 (TCC)
- ALE Heavylift v MSD (Darlington) Limited [2006] EWHC 2080 (TCC)
- Lead Technical Services v CMS Medical [2007] EWCA Civ 316)
- T & T Fabrications v Hubbard [2008] EWHC B7 (TCC)
- Debeck Ductwork Installation Ltd v T&E Engineering Ltd, Unreported October 14 [2002] TCC
- Hatmet Ltd v Herbert [2005] EWHC 3259 TCC
- Cowlin Construction Limited v CFW Architects [2002] EWHC 2914 TCC
Cite this Page
Adjudicators` Jurisdiction and Construction Contracts. (2019, Apr 14). Retrieved from https://phdessay.com/adjudicators-jurisdiction-and-the-requirement-for-construction-contracts-in-writing-a-view-on-the-impact-of-legislative-change/
Run a free check or have your essay done for you