Applying Management Theories

Last Updated: 23 Mar 2023
Pages: 4 Views: 161

The group cited that their first action would be to organize a group meeting in the week, before the next company meeting, a good pro-active decision. It was observed that no leadership took place in the group with everyone inputting questions that the group could not answer. The Part D students were then able to answer some questions. In the meeting the group did not discuss project strategy, but discussed sensor systems, there was no clear sensory system decided with A. Shabbier wanting to research into sonar systems and A. Mohammed continuing research into IR sensors and QUIT sensors. Over the next two weeks the group began to realize their task and formed their project structure based on the diagram. The strategy overall was carried out well throughout the group, as they became more aware of mistakes that may have occurred without the plan and check stages. Once the strategy was in place, the Plan section was implemented. Within the plan stage the group took into account the following factors for equipment choice: Cost, Complexity and Acceptability.

An example of this method was the choice of sensors, the group decided to use IR sensors, as they were cheaper than sonar systems, they were the east complex of all the systems and achieved the groups' requirements. This decision-making process was very powerful, as it gave the groups specific criteria that they had to uphold and it prevented members from verging off-topic, which they were prone to doing.

Their failure resulted in a leaderless structure to the group, immediately disadvantaging the group, as there was no one to make key decisions. This can be seen by tensions formed in the group with regards to sub-systems. The group decided to create sub-systems and allocate a person per sub-system, though this was a sensible systematic approach (though it could have been improved by using at a job design chart. Breaking down the sub-systems affected the group with some tasks much simpler and straightforward than others. This process led to J. Peters and A. Mohammed wanting the same roles.

Order custom essay Applying Management Theories with free plagiarism report

feat icon 450+ experts on 30 subjects feat icon Starting from 3 hours delivery
Get Essay Help

The decision was made by the rest of the group that A. Mohammed would be better suited to the desired role. J. Peters had little contact with the group up until that point and this showed in the groups' decision. J. Peters was left with the difficult task of producing the interim report for the group. This was a poor decision by the group as it meant that they issue also arose from the sub-system approach, where during one week; more than one member of the group was absent. This led to a halt in progress of the project in the areas where team members were away, as absent team members knew their role, but the other team members did not.

This should have been factored into the projects' risk contingency plan; however this was yet to be created by J. Peters. This failure resulted in a week without progress and certainly created tension not only thin the group, but between the group and supervisor as well. A better strategy would have been to split the design into sub-systems, but within each sub-system, tasks could be created and given to members of the group, allowing more than one group member to have knowledge of each sub-system to ensure progress continues.

What sequence? Who else? How to interface with the facilities? Environmental conditions? How much autonomy? Skills? Where to locate? Tasks? After the fourth week it was clear that A. Shabbier had taken charge of the project, which could be a positive factor of not immediately selecting a group leader, as it allowed time for the more dedicated person the project to take control, effectively becoming the natural leader.

His indecision however, led to a long delay within an exercise the group carried out. A requirement that the group made was to increase the speed of the robot. The group originally removed the wheel and replaced it with a larger wheel increasing the speed, a good idea; however, their plan did not consider that they were not allowed to remove parts from the Boot. Therefore the approach taken by the group was to use their project PICA strategy and they were able to modify the wheel by creating an extension to use the original wheel as a shaft for a larger wheel.

This shows good initiative from the group, however the issue should not and would limitation control. The group would have been better to choose a product design strategy, where they generated a concept, which they could feedback to the supervisor in a company meeting, who could then evaluate the groups' design, making sure it is suitable for the set requirements. This would make sure the design fits the requirements and if not, it could be improved until it did. The groups' strategy for their hardware sub-system had certain requirements, one of which included a LED display.

The display was a creative concept as many ideas in the group were; however there was a delay in delivery (due to the University) which the group had not planned for. This delay was unplanned for with no risk contingency plan in place. This therefore meant the group had to alter their Giant chart to their needs at that time. This was poorly planned, as a better Giant chart would have had extra time allocated for work that could not be completed at the specific time.

Cite this Page

Applying Management Theories. (2018, Aug 14). Retrieved from https://phdessay.com/applying-management-theories/

Don't let plagiarism ruin your grade

Run a free check or have your essay done for you

plagiarism ruin image

We use cookies to give you the best experience possible. By continuing we’ll assume you’re on board with our cookie policy

Save time and let our verified experts help you.

Hire writer