DU Singer Hospital Products Corp. (Adapted from Meredith and Mantel) D. U. Singer Hospital Products Corp. has done sufficient new product development at the research and development level to estimate a high likelihood of technical success for a product of assured commercial success: A long-term antiseptic. Management has instructed Singer’s Antiseptic Division to make a market entry at the earliest possible time; they have requested a complete plan up to the startup of production.

Project responsibility is assigned to the division’s research and development group; Mike Richards, the project scientist who developed the product is assigned responsibility for project management. Assistance will be required from other parts of the company: Packaging task force, R&D group, Corporate engineering, and Corporate purchasing. Mike was concerned about the scope of the project. He knew from his own experience that a final formula had yet to be developed, although such development was really a “routine” function.

The remaining questions had to do with color, odor, and consistency additives rather than any performance-related modification. Fortunately, the major regulatory issues had been resolved and he believed that submission of regulatory documentation would be followed by rapid approval as they already had a letter of approval contingent on final documentation. Mike was concerned about defining the project unambiguously. To that end, he obtained an interview with S. L. Mander, the group vice-president.

Order custom essay Project Planning with free plagiarism report

feat icon 450+ experts on 30 subjects feat icon Starting from 3 hours delivery
Get Essay Help

When he asked Mander where his responsibility should end, the executive turned the question back to him. Mike had been prepared for this and said that he would like to regard his part of the project as done when the production process could be turned over to manufacturing. They agreed that according to Singer practice, this would be when the manufacturing operation could produce a 95% yield of product (fully packaged) at a level of 80% of the full production goal of 10 million liters per year. But I want you to remember,” said Mander, “that you must meet all current FDA, EPA, and OSHA regulations and you must be in compliance with our internal specification - the one I have got is dated September and is RD78/965. And you know that manufacturing now - quite rightly, I feel - insists on fully documented procedures. ” After this discussion, Mike felt that he had enough information about this aspect to start to pin down what had to be done to achieve these results. His first step in this effort was to meet with P. H. Docent, the director of research. You are naive if you think that you can just start right in finalizing the formula,” said Docent. You must first develop a product rationale (a). This is a formally defined process according to company policy.

Marketing expects inputs at this stage, manufacturing expects its voice heard, and you will have to have approvals from every unit of the company that is involved. You should have no trouble if you do your homework, expect to spend a good eight weeks to get this done. ” “That certainly stretches things out,” said Mike. I expected to take 12 weeks to develop the ingredient formula (b) and you know that I can’t start to establish product specifications (c ) until the formula is complete. That’s another 3 weeks. ” “Yes, but while you are working on the product specifications you can get going on the regulatory documentation (d). Full internal specifications are not required for that work, but you can’t start those documents until the formula is complete. ” “Yes, and I find it hard to believe that we can push through both preparation of documents and getting approval in 3 weeks, but Environmental swears it can be done. “Oh, it can be done in this case because of the preparatory work. Of course, I won’t say that this estimate of 3 weeks is as certain as our other estimates. All we need is a change of staff at the Agency and we are in trouble. But once you have both the specifications, and the approval, you can immediately start on developing the processing system (g). ” "Yes, and how I wish we could get a lead on that, but the designers say that there is too much uncertainty and they won't move until they have both specifications and regulatory documentation and approval.

They are offering pretty fast response; six weeks from start to finish for the processing system. " "They are a good crew, Mike. And of course, you know that you don't have to delay on starting the packaging segment of this project. You can start developing the packaging concept (e) just as soon as the product rationale has been developed. If my experience is any judge, it will take a full eight weeks; you'll have to work to keep the process from running forever. " "But as soon as that is finished we can start on the design of the package and its materials (f) which usually takes about six weeks.

Once that is done we can start on the packaging system (h) which shouldn't take longer than eight weeks," concluded Mike. At this point he realized that although Docent would have general knowledge, he needed to talk directly to the Director of Manufacturing. "The first step, which follows the completion of the development of processing and packaging systems," said the Director of Manufacturing, "is to do a complete study of the facilities requirements (i). You won't be able to get that done in less than four weeks.

And that must precede the preparation of the capital equipment list (j) which should take about three-quarters as long. Of course, as soon as both the process system and packaging system are completed, you could start on preparing the written manufacturing procedures (q). " "But, said Mike, "Can I really finish the procedures before I have installed and constructed the facilities (p)? " "No, quite right. What you can do is get the first phase done, but the last phase will have to wait for the installation and construction. "Then this means that I really have two phases for the writing, that which can be completed without the installation and construction (q), which will take seven weeks, and that which has to wait for those inputs (q? ) which will require 3 weeks. " "True. Now you realize that the last thing you have to do is to run the equipment in a pilot test ® which will show that you have reached a satisfactory level? " "Yes. Since that must include debugging, I've estimated a six-week period as adequate. " The director of manufacturing assented. Mike continued, "What I'm not sure of is whether we can run all the installation tasks in parallel. "

Cite this Page

Project Planning. (2017, Jan 25). Retrieved from https://phdessay.com/project-planning/

Don't let plagiarism ruin your grade

Run a free check or have your essay done for you

plagiarism ruin image

We use cookies to give you the best experience possible. By continuing we’ll assume you’re on board with our cookie policy

Save time and let our verified experts help you.

Hire writer