Aib Problem Solution

Last Updated: 25 May 2020
Pages: 2 Views: 410

Aib Homework Wk3 Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (2 points) 32 -> CORRECT b) What is the Critical Path of the Project? (3 points) B,D,F,G,I -> CORRECT 2,4,6,7,9 c) What is the ES for Activity D? (2 points) 6 -> Correct ) What is the LS for Activity G? (2 points) 15 e) What is the EF for Activity B? (2 points) 6 -> Correct f) What is the LF for Activity H? (2 points) 32 -> Correct g) What is the float for Activity I? (2 points) 0 Problem 2 The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) ) Calculate the scheduled completion time. (3 points) 30 b) Identify the critical path (4 points) B,C,D,F,H c) What is the slack time (float) for activity A? (2 points) 5 d) What is the slack time (float) for activity D? (2 points) 0 e) What is the slack time (float) for activity E? (2 points)4 f) What is the slack time (float) for activity G? (2 points) 5 Problem 3 The following data were obtained from a project to design a new software package: Activity Duration Predecessors A 5 Days --- B 8 Days --- C 6 Days A D 4 Days C, B E 5 Days A F 4 Days D, E, G G 4 Days B, C H 3 Day G

Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) e) Calculate the scheduled completion time. (3 points) 19 f) Identify the critical path(s) (4 points) A,C,D,G,F g) What is the slack time (float) for activity B? (2 points) 3 h) What is the slack time (float) for activity D? (2 points) 0 e) What is the slack time (float) for activity E? (2 points) 5 f) What is the slack time (float) for activity G? (2 points) 0 Problem 4 The following data were obtained from an in-house MIS project: Activity Duration Predecessors

A 5 Days --- B 8 Days --- C 5 Days A D 4 Days B E 5 Days B F 3 Day C, D G 7 Days C, D H 6 Days E, F, G I 9 Days E, F Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (3 points) 25 b) Identify the critical path (4 points) B,D,G,H c) What is the slack time (float) for activity A? (2 points) 2 d) What is the slack time (float) for activity D? (2 points) 0 e) What is the slack time (float) for activity E? (2 points) 3 f) What is the slack time (float) for activity F? (2 points) 1

Order custom essay Aib Problem Solution with free plagiarism report

feat icon 450+ experts on 30 subjects feat icon Starting from 3 hours delivery
Get Essay Help

Cite this Page

Aib Problem Solution. (2018, Jan 15). Retrieved from https://phdessay.com/aib-problem-solution/

Don't let plagiarism ruin your grade

Run a free check or have your essay done for you

plagiarism ruin image

We use cookies to give you the best experience possible. By continuing we’ll assume you’re on board with our cookie policy

Save time and let our verified experts help you.

Hire writer